Previous Page  86 / 116 Next Page
Information
Show Menu
Previous Page 86 / 116 Next Page
Page Background

8 6

PLUMBING CONNECTION Summer 2017

The arguably most critical

requirement is that the contractor’s or

builder’s work complies with the law.

Finally, the work should be carried

out by the promised due date. Though

this duty is not often explicitly stated

in the law (although it is in Victoria in

the Domestic Building Contracts Act)

it is related to the critical element of

time. It is also usually the subject of a

clause in the contract where there are

a specified number of days by which the

works must reach practical completion

or substantial completion.

It is specified in the contract what

the consequences are if this date is

not achieved. Liquidated damages

may be payable, based on the number

of days past the due date the works

are complete is an example. A set

rate is usually set, such as $250 per

week. There are exceptions to this

requirement for the builder to pay such

damages, broadly based on factors

outside the builder’s control.

Mention should be made of the

important topic of certification of

works. Certification of works can be

implied or actual - usually written,

but it can be verbal.

The builder can be

entitled to final

payment claims

based on an implied

written statement

from the architect or

inspector.

The most

common examples

of documentation

are final and

practical completion

certificates. Often,

a building contract

says that a certificate from an architect

is required to indicate that the architect

is satisfied that the works carried

out are satisfactory in relation to the

contract. In general, the certificates

referred to in this article are conclusive

with respect to compliance of the duties

or standards but this can depend on

what the contract stipulates.

Final certificates are usually issued

at the end of the

defects period.

However if there are

defective works,

an owner can still

usually, despite

the certificate,

claim damages.

As in all cases, it

is the contract

and its wording

which governs the

conclusiveness or

otherwise of a final

certificate.

Due to the often discrete and

technical aspects of this area, it is

strongly recommended that if you are

faced with allegations that you have

done work of sub-standard quality, you

seek professional advice.

ARE YOU GETTING

YOUR REGULAR

NEWSLETTER?

www.build.com.au/newsletters

Building

standards apply

whether or not

thay are written

VSHFL¿FDOO\ RU DUH

even referred to in

the contract

LEGAL EAGLE