Previous Page  42 / 116 Next Page
Information
Show Menu
Previous Page 42 / 116 Next Page
Page Background

4 2

PLUMBING CONNECTION

SPRING 2016

LEGAL MATTERS

PAUL COTT

DAMAGES FOR BUILDING

CONTRACT BREACHES

T

here are multiple ways that a building owner or

builder (including subcontractors and others such as

architects for example, among others) can breach

a building contract. Some of the main ways that such

breaches can occur include the following: not paying monies

owed on time or at all, ‘locking out’ builders from sites,

not supplying specified goods and/or services, stopping or

suspending work on a project, conducting defective works

and interfering with works among others.

REMEDIES

Apart from obtaining from a court or a tribunal (VCAT

in Victoria) an order for specific performance (an order

directing a party to perform its contractual obligations)

or an injunction (an order prohibiting or compelling a

party to do something) a key remedy a party can obtain in

circumstances as described above is damages.

Often the type of, and the extent of the remedy awarded,

depends on how significant the breach is, how many

breaches there are, and whether the breaches are ‘as to’

fundamental terms (such as terms as to payment or as to

time for completion) of the contract or less fundamental

ones.

Damages are awarded with the objective of providing

recompense or reimbursement to someone for actual

financial loss incurred as a result of, or caused by (in law)

another party’s breach of contract.

They are not, as is commonly thought, awarded to provide

punishment for someone having done something wrong.

They are not meant to be ‘penal’ or ‘punitive’ in character,

even though, commonly, the innocent party sees the ‘guilty’

party as deserving of punishment (even if, in a moral sense,

they are).

In the building (and generally) contract setting, damages

are meant to put the innocent party in the same position

as they would have been in if the contract breach had not

occurred.

MEASURE OF DAMAGES – HOWMUCH?

Courts and/or tribunals calculate the amount of damages

to be awarded by how much, as above, a party is said to

have lost as a result of the contract breach. They will award

an amount which will, or which will likely, as close as it is

PAUL COTT

EXPLAINS SOME OF THE MYRIAD WAYS BUILDING CONTRACTS CAN BE BREACHED AND WHAT ACTIONS

TO TAKE SHOULD YOU FIND YOURSELF IN THE UNFORTUNATE CIRCUMSTANCE.

possible to do so, bring a party back into the position they

would have been in had the contract not been breached.

Any damages awarded must flow as a natural result of the

breach and not as a consequence of something else or what

someone did or did not do. Basically, what we are saying is

that the losses being claimed for must be ‘caused by’ the

breach by the other party to the contract.

Note that it is possible for both parties to a building

contract, if they are both at fault in the sense of breaching

the contract either simultaneously or separately, to be

awarded damages (and on the converse, have damages

awarded against them).

Just because a court or a tribunal finds it very difficult,

even nigh on impossible to calculate what actual damages

will be awarded (for example, it will nearly always be required

to factor in contingencies into such calculations, so in

that sense awarding damages is to some extent based on

a prediction as to future events, damages being based on

what would have been the situation less a breach) does not

mean damages will not be payable.